Two Roads Development has started demolishing the 13-story Biscayne 21 condominium at 2121 North Bayshore Drive, the bayfront site where it plans EDITION Residences, Miami Edgewater: a 55-story, 649-foot tower of 185 residences. The work follows a settlement with the building’s last holdout owners after a dispute that began in 2023. For buyers, it is the first physical progress at the site in more than three years. It is site preparation, not the start of the tower.

Demolition underway · Vertical construction not yet reported · No published completion date

Independent buyer research · Not affiliated with Two Roads Development, EDITION, Marriott International or Douglas Elliman

Artist's rendering of the planned EDITION Residences glass tower on the Edgewater shoreline of Biscayne Bay at golden hour, with Margaret Pace Park and the downtown Miami skyline beyond.
EDITION Residences, Miami Edgewater, artist’s rendering. Rendering: Two Roads Development; the finished building may differ.
The Short Version

Four answers, as of November 13, 2026

What happened?
Two Roads Development announced on November 11, 2026 that demolition had begun at the Biscayne 21 site. Miami-Dade County records show a total-demolition permit issued on August 26, 2026, permit number 2026067492, according to Florida YIMBY.
Why did it take so long?
Holdout owners challenged the termination of the Biscayne 21 condominium in 2023 and won on appeal. Two Roads then reached and funded a settlement, first reported on August 31, 2026, that was reported at about $50 million.
Has the tower started?
No. Demolition clears the site. Foundation work and vertical construction have not been reported, and the developer has not published a completion date.
What should a buyer do?
Treat demolition as reduced site risk, not removed development risk. Check your contract’s completion date, extension clauses and deposit terms before relying on any schedule. The buyer section explains what to ask.
Demolition and Construction Status

The site is being cleared. The tower has not started.

Current stageDemolitionAnnounced November 11, 2026 · Biscayne 21 building
Demolition permitNo. 2026067492Total demolition, issued August 26, 2026, per county records cited by Florida YIMBY
FoundationsNot reportedNo foundation work has been announced
Vertical constructionNot reportedA vertical-construction permit application was filed in December 2023
CompletionNo published dateThe developer has not announced a delivery target

“Demolition marks the beginning of a new chapter for this exceptional waterfront site,” Taylor Collins, managing partner of Two Roads Development, said in the announcement. What has begun is the removal of the existing 13-story building. Neither the developer nor the reporting describes foundation work, a construction start date for the tower, a general contractor mobilization or a completion target.

Demolition also came later than first described. In early September, Two Roads told Commercial Observer that demolition would take place that month, with vertical construction to follow soon after; the announcement came in November. A two-month slip at this stage is not unusual, but it is a reminder that a developer’s near-term schedule is a plan, not a commitment.

What comes next is typically site clearing, seawall and foundation work, then the tower itself. Florida YIMBY reported in December 2023 that Two Roads had filed a permit application for vertical construction, with separate applications for demolition and a seawall. We have not confirmed whether the building permit for the tower has been issued. Our Ziggurat Coconut Grove demolition analysis and Mandarin Oriental Miami groundbreaking report show how far apart site work and vertical construction can be.

Project Overview

55 stories, 185 residences, serviced by EDITION

EDITION Residences, Miami Edgewater is planned as a glass-clad, 55-story, 649-foot tower designed by Bernardo Fort-Brescia of Arquitectonica, with interiors by Studio Munge and landscape architecture by EDSA. Two Roads uses the EDITION name under license from Marriott International, and EDITION Hotels is slated to manage and operate the building. Two Roads also developed Elysee, an Arquitectonica-designed tower in Edgewater.

The 185 residences range from one-bedroom-plus-den to four-bedroom layouts with private terraces and floor-to-ceiling windows. The latest announcement gives sizes of about 1,922 to 3,760 square feet; earlier published specifications cited 1,952 to 3,864, so confirm the size and measurement method of any specific residence in the contract. Earlier plans also include three tri-level penthouses with private rooftop pools and gardens.

About 45,000 square feet of amenities are planned, including a lobby and lounge, fitness center, yoga studio, spa services from EDITION, children’s and teen rooms, a multi-sport simulator and two pickleball courts. In September, a Two Roads representative told Commercial Observer the project was about 40 percent sold; that figure is developer-reported and unverified. Pricing and availability change, so we confirm both directly for each buyer. For the full project profile, see our EDITION Residences buyer-rebate guide.

Artist's rendering of an EDITION Residences great room with an open kitchen, dining table and living area facing floor-to-ceiling windows over Biscayne Bay.
A residence great room, artist’s rendering. Rendering: Two Roads Development.
The Edgewater Location

More than 800 feet of Biscayne Bay, next to Margaret Pace Park

The 3.5-acre site sits on North Bayshore Drive between Northeast 21st and 22nd Streets in southern Edgewater, immediately north of Margaret Pace Park and between the Venetian and Julia Tuttle causeways. It has more than 800 linear feet of bay frontage, and plans connect it to the Miami Baywalk and the park. That is an unusually long water edge for a single Edgewater site, and the neighbor to the south is a public park rather than a development parcel.

For a luxury buyer, that combination of direct bayfront, park access and a short drive to downtown Miami and the Design District is what the premium pays for. It also creates a question worth asking. When the project launched in 2022, plans for the full 3.5-acre site described three towers, so ask what is planned on the rest of the land and how that construction could affect views, access and assessments. Our Edgewater buyer guide compares the neighborhood’s other bayfront projects, including Villa Miami, Aria Reserve and Anantara Miami.

What This Means for Pre-Construction Buyers

Lower site risk, not lower development risk

What demolition shows

  • Site control is resolved. The obstacle that stopped the project for three years, the holdout owners, has been settled.
  • Money is going into the ground. A developer that pays to demolish a building is committing capital to the site, not just to marketing.
  • Permits are moving. A total-demolition permit was issued, and a tower permit application has been on file since 2023.

What it does not show

  • That the tower is financed. We have not found a reported construction loan for the tower.
  • When it will be finished. No completion date has been published, and the near-term schedule has already slipped.
  • That your deposit is protected. Your protection comes from Florida law and your contract, not from progress at the site.

Completion dates in existing contracts

The delay already has a legal history of its own. In May 2026, The Real Deal reported that three buyers who signed contracts for five residences in spring 2023 sued Two Roads to recover about $2.5 million in deposits, saying their units had been expected by summer 2028. Collins called the claims without merit and said the contracts are clear on the issue. We have not found a reported outcome. Whatever happens in that case, the lesson for every buyer is the same: the date that binds the developer is the outside completion date in your contract, together with its extension and delay clauses, not the date in a sales presentation.

Deposit exposure

Under Florida Statute §718.202, the first 10% of the price paid before closing must be held in escrow. Payments above 10% may be used for construction once construction has begun, if the contract allows it and carries the required bold-type disclosure on its first page. The statute’s list of permitted construction costs includes demolition and site clearing. Ask your attorney whether, under your contract, demolition starts that clock. Our Faena Residences analysis explains the statute in detail.

Before you sign, or before your next deposit

1. Outside completion date and extensions: what the contract allows, and whether the developer has invoked any delay provisions. 2. Deposit schedule and escrow agent: how much is due before closing and who holds it. 3. Construction-use clause: whether deposits above 10% can be spent, and from when. 4. Changes since your offering: sizes, layouts or amenities that differ from your documents. 5. Budget: the developer’s estimated operating budget, not a verbal estimate. 6. The rest of the site: what may be built next door. Our South Florida pre-construction buyer guide covers each step.

Buyer Representation and Commission Rebates

Have someone on your side before you visit the sales gallery

EDITION Residences is sold through the developer’s sales team, which works for the seller. Nobody there is paid to tell you what the delay history means for your contract or how your price compares with the rest of Edgewater. That is the job of a buyer’s agent, and the order matters: register with your own representative before your first contact with the developer. Our guide to Miami pre-construction broker registration explains why.

TheBuyerRebate.com and Jordan Real Estate represent buyers independently, with attorney-reviewed transaction support. Eligible buyers may receive up to 50% of our buyer-agent commission back at closing. Whether a rebate applies, and how much, depends on the compensation the developer makes available in your transaction, your representation agreement and lender and closing requirements. A rebate is never guaranteed, and we confirm the figure in writing before you sign. See how it works in our Miami pre-construction buyer rebate guide.

Check Your Rebate Estimate Your EDITION Rebate

Artist's rendering of the planned EDITION Residences garden pool lined with loungers, palms and bougainvillea, with Biscayne Bay beyond.
The planned garden pool on the bay, artist’s rendering. Rendering: Two Roads Development.
Buyer Representation

Considering EDITION Residences? Talk to us before you contact the sales gallery.

We can review the completion and deposit terms with you and your attorney, compare pricing with other Edgewater bayfront projects, and estimate the rebate available in your transaction. Eligible buyers may receive up to 50% of our buyer-agent commission back at closing. Rebates are never guaranteed and are confirmed in writing before you sign.

(786) 550-6294

Check Your EDITION Residences Rebate

No obligation. This form does not register you with the developer or any sales gallery.

See our Privacy Policy and Terms of Use.

Research & Sources

What this page is based on

Research cutoff: November 13, 2026. Project specifications are developer statements as reported. Permit details come from Miami-Dade County records as cited by Florida YIMBY; the permit file and the court dockets were not reviewed directly.

Source Register

  • Florida YIMBY · November 12, 2026Demolition Begins At Site Of 649-Foot EDITION Residences In Miami’s Edgewater
    Supports: demolition commenced, permit 2026067492 issued August 26, 2026, 55 stories and 649 feet, 185 residences, design team, 1,922 to 3,760 square feet, amenities, EDITION Hotels as operator, location between NE 21st and 22nd Streets, 800-plus feet of frontage, Collins quotation.
  • PROFILEmiami · November 12, 2026Two Roads Begins Demolition for EDITION Residences in Miami’s Edgewater
    Supports: developer announcement dated November 11, residence count and sizes, amenities.
  • Commercial Observer · September 2026Two Roads Settles Biscayne 21 Condo Suit, Paving Way for Edition Condo in Miami
    Supports: $50 million for remaining units per a Two Roads representative, demolition planned for September with vertical construction soon after, about 40 percent sold, 2022 acquisition, The Real Deal as first to report.
  • Florida YIMBY · September 2, 2026Two Roads Reaches Settlement With Biscayne 21 Owners
    Supports: settlement reached and fully funded, owners agreeing to sell, Supreme Court declining review, circuit court restoration order.
  • Bisnow · September 2026 and October 2025Developer To Pay Biscayne 21 Holdouts $50M; Florida Supreme Court Rejects Biscayne 21 Buyout Appeal
    Supports: 10 owners, 100% to 80% threshold, March 2024 appeals ruling, July 2025 rehearing denial, October 2025 Supreme Court decision, January 2026 restoration order.
  • The Real Deal · May 14, 2026Edition Residences condo buyers sue Two Roads over stalled project
    Supports: three buyers, five units, spring 2023 contracts, expected summer 2028 completion, Collins response. Deposit amount from The Real Deal, July 13, 2026.
  • Florida YIMBY · December 2023 and September 2022Vertical construction permit application; project unveiling
    Supports: December 5, 2023 permit application, separate demolition and seawall applications, earlier 1,952 to 3,864 square feet, three-tower plan for the 3.5-acre site.
  • Florida Legislature · 2026 Florida StatutesSection 718.202, Sales or reservation deposits prior to closing
    Primary source for the deposit and escrow rules described above.

Independence and status. TheBuyerRebate.com / Jordan Group is not affiliated with Two Roads Development, EDITION, Marriott International, Douglas Elliman or any party named here. This page is independent buyer-advisory editorial content. Status is described as of November 13, 2026 and will change. Project specifications, sales figures and schedules are developer statements that have not been independently verified. The renderings are the developer’s conceptual images, reproduced for editorial context, and the completed building may differ. Nothing here is an offer to sell or a solicitation to buy real estate, and nothing here is legal, tax or financial advice; the discussion of Florida Statute §718.202 is a general explanation, and your contract should be reviewed by a Florida attorney. Rebate amounts depend on the compensation actually received on each transaction and, where financing is involved, lender approval of credits; a rebate is never guaranteed. Information is deemed reliable but is not guaranteed and is subject to change without notice.